Florida Department of Transportation Project Starts Week Of April 18
The Florida Department of Transportation (FDOT) is scheduled to begin a roadway project the week of April 18, 2022, along Overseas Highway in Monroe County from mile markers 73.8 to 76.
WORK TO BE PERFORMED
The Florida Department of Transportation (FDOT) is scheduled to begin a roadway project the week of April 18, 2022, along Overseas Highway in Monroe County from mile markers 73.8 to 76.
WORK TO BE PERFORMED
- Repaving and restriping the roadway and shoulders
- Raising the roadway and shoulders from approximately MM 73.8 to MM 76.0
- Improving drainage
- Tying new roadway into the shoreline protection system along Sea Oats Beach and adding a guardrail system
- Upgrading roadway signage
- Upgrading bicycle features at the shared-use path crossing locations
- Upgrading thermoplastic pavement markings from MM 70.0 to MM 80.0
- Travel lanes and sidewalks may be closed only during non-peak hours on non-event days/nights/weekends. Non-peak hours are:
9:30 p.m. to 5:30 a.m., Sunday through Thursday
Est. Completion: Summer 2022
Construction Cost: $18.1 million
Lengths and Limits
State Road (SR) 5/US 1/Overseas Highway from south of Tollgate Boulevard Mile Marker (MM) 73.75 to Lignumvitae Channel (MM 77.5) and from MM 70.0 to MM 80.0
For more information, CLICK HERE.